Resurfacing programme June/​July 2019
From 16 June to 4 July 2019, roads in the vicinity of Lambeth North will be resurfaced during the night-time. This includes Westminster Bridge Road, from York Road to Morley Street. The exact programme and diversion plans are below.
All works will take place between 10.00pm-5.00am, Sunday-Thursday:
- Sunday 16 June: whole junction
- Monday 17 June: whole junction
- Tuesday 18 June: Kennington Road north bound
- Wednesday 19 June: Kennington Road north bound
- Thursday 20 June: contingency date
No works Friday and Saturday.
- Sunday 23 June: Westminster Bridge Road east bound
- Monday 24 June: Westminster Bridge Road east bound
No works Friday and Saturday.
- Sunday 30 June: Westminster Bridge Road west bound
- Monday 1 July: Westminster Bridge Road east bound
- Tuesday 2 July: contingency date